← The Roadmap Reckoner: scorecard and every promise

Did Orlando make its fare-free LYMMO downtown buses 100% zero-emission by 2025, as it said in 2020?

The Roadmap Reckoner · Downtown Orlando (LYMMO, the fare-free downtown circulator) · last checked 2026-11-07

VerdictPENDING, OVERDUE (by 10 months and 7 days)
PromiserCity of Orlando (LYMMO is run by LYNX)
PlaceDowntown Orlando (LYMMO, the fare-free downtown circulator)
Promised2025-12-31 ("to a 100% zero-emissions fleet by 2025", the City of Orlando's release last updated Oct. 28, 2020)
Delivered / statusNot met: the 14 electric buses reached LYMMO late; in LYNX's 2025 fiscal year, CNG buses ran on LYMMO routes "due to electric vehicle downtime"; in May 2026, "the electric fleet being largely out of service"
Last checked2026-11-07

Verdict: PENDING, OVERDUE, by 10 months and 7 days. In a release last updated on October 28, 2020, the City of Orlando set "the city's sustainability goal for transitioning LYMMO, downtown Orlando's fare-free circulator, to a 100% zero-emissions fleet by 2025." [C1, C2] Reading "by 2025" as by the end of 2025, the latest the words allow, the goal is 10 months and 7 days overdue at this entry's last check [C2]. The 14 electric buses the release named did reach LYMMO, late. The release's date for them was 2021 [C4]. LYNX's August 2023 minutes list the last six among the "past year's accomplishments" [C19, C20, C21], and in May 2024 LYNX, which runs LYMMO, said it "operates fourteen (14) battery electric buses (BEB) on the LYMMO service." [C25, C26] But in its 2025 fiscal year, LYNX's results say "Increased costs were driven by CNG vehicle usage on LYMMO routes due to electric vehicle downtime." [C40, C41, C42] In May 2026, its amended budget gives "the electric fleet being largely out of service." [C28, C30]

Last checked: November 7, 2026.

Re-checked November 7, 2026. LYNX's meeting page for October 2026 lists a Finance and Audit Committee package, an Oversight Committee package and a Board package [C48, C49, C50]. The text of each was searched for electric buses, battery electric buses, zero-emission, downtime, Proterra and the electric fleet, with no match in any, so none of them mentions the LYMMO electric buses, their downtime or the zero-emission goal in those words [C48, C49, C50]. The city's release still returns "Error 404 - Page Not Found - City of Orlando" [C51]. The verdict is unchanged; the delay is counted to this check.

Corrected 20 October 2026: a sentence on the LYNX fleet plan was reworded. The minutes give two points about battery electric buses, repair time and charging time, and the sentence now says both. The verdict and every date in the timeline are unchanged.

The promise

The City of Orlando's release, "Last updated on October 28, 2020", announced the first electric LYMMO bus [C1, C2]. LYMMO is downtown Orlando's fare-free circulator, and LYNX runs it [C2, C26]. The release said:

"This electric bus is the first investment toward achieving the city's sustainability goal for transitioning LYMMO, downtown Orlando's fare-free circulator, to a 100% zero-emissions fleet by 2025. In addition to this electric bus, seven additional zero-emission, all-electric buses will be added to service by the end of this year." [C2, C3]

It went on: "Also in 2021, through additional FTA grant funding, six more electric buses will also be added which will bring the zero-emission fleet of LYMMO buses to a total of 14." [C4]

Timeline

What changed, and why, in the record's own words

What it cost

What is still open

What this entry did not check

Sources

  1. C1 https://web.archive.org/web/20210427193441/https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet
  2. C2 https://web.archive.org/web/20210427193441/https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet
  3. C3 https://web.archive.org/web/20210427193441/https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet
  4. C4 https://web.archive.org/web/20210427193441/https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet
  5. C5 https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet
  6. C8 https://oucblog.com/first-of-14-e-buses-arrives-in-orlando/
  7. C9 https://oucblog.com/first-of-14-e-buses-arrives-in-orlando/
  8. C10 https://oucblog.com/first-of-14-e-buses-arrives-in-orlando/
  9. C11 https://www.golynx.com/core/fileparse.php/97315/urlt/2-24-2022-Board-Report-Pkg.pdf
  10. C12 https://www.golynx.com/core/fileparse.php/97315/urlt/3-24-2022-Board-Report-Pkg.pdf
  11. C13 https://www.golynx.com/core/fileparse.php/97315/urlt/3-24-2022-Board-Report-Pkg.pdf
  12. C14 https://www.golynx.com/core/fileparse.php/97315/urlt/3-24-2022-Board-Report-Pkg.pdf
  13. C15 https://www.golynx.com/core/fileparse.php/97315/urlt/3-24-2022-Board-Report-Pkg.pdf
  14. C16 https://www.golynx.com/core/fileparse.php/97315/urlt/3-24-2022-Board-Report-Pkg.pdf
  15. C17 https://www.golynx.com/core/fileparse.php/97315/urlt/6-23-2022-Board-Report-Pkg.pdf
  16. C18 https://www.golynx.com/core/fileparse.php/97315/urlt/6-23-2022-Board-Report-Pkg.pdf
  17. C19 https://www.golynx.com/core/fileparse.php/97315/urlt/9-28-2023-Board-Report-Pkg.pdf
  18. C20 https://www.golynx.com/core/fileparse.php/97315/urlt/9-28-2023-Board-Report-Pkg.pdf
  19. C21 https://www.golynx.com/core/fileparse.php/97315/urlt/9-28-2023-Board-Report-Pkg.pdf
  20. C22 https://www.golynx.com/core/fileparse.php/97315/urlt/9-28-2023-Board-Report-Pkg.pdf
  21. C23 https://www.golynx.com/core/fileparse.php/97315/urlt/3-28-2024-Board-Report-Pkg.pdf
  22. C24 https://www.golynx.com/core/fileparse.php/97315/urlt/3-28-2024-Board-Report-Pkg.pdf
  23. C25 https://www.golynx.com/core/fileparse.php/97315/urlt/5-23-2024-Board-Report-Pkg.pdf
  24. C26 https://www.golynx.com/core/fileparse.php/97315/urlt/5-23-2024-Board-Report-Pkg.pdf
  25. C27 https://www.golynx.com/core/fileparse.php/97315/urlt/5-23-2024-Board-Report-Pkg.pdf
  26. C28 https://www.golynx.com/core/fileparse.php/97315/urlt/5-28-2026-Board-Report-Pkg.pdf
  27. C29 https://www.golynx.com/core/fileparse.php/97315/urlt/5-28-2026-Board-Report-Pkg.pdf
  28. C30 https://www.golynx.com/core/fileparse.php/97315/urlt/5-28-2026-Board-Report-Pkg.pdf
  29. C31 https://www.golynx.com/core/fileparse.php/97315/urlt/6-25-2026-Board-Report-Pkg.pdf
  30. C32 https://www.golynx.com/core/fileparse.php/97315/urlt/6-25-2026-Board-Report-Pkg.pdf
  31. C33 https://www.golynx.com/core/fileparse.php/97315/urlt/4-24-2025-Oversight-Committee-Pkg.pdf
  32. C34 https://www.golynx.com/core/fileparse.php/97315/urlt/4-24-2025-Oversight-Committee-Pkg.pdf
  33. C35 https://www.golynx.com/core/fileparse.php/97315/urlt/4-24-2025-Oversight-Committee-Pkg.pdf
  34. C36 https://www.golynx.com/core/fileparse.php/97315/urlt/4-24-2025-Oversight-Committee-Pkg.pdf
  35. C37 https://www.golynx.com/core/fileparse.php/97315/urlt/8-21-2025-Finance-Audit-Committee-Pkg.pdf
  36. C38 https://www.golynx.com/core/fileparse.php/97315/urlt/8-21-2025-Finance-Audit-Committee-Pkg.pdf
  37. C39 https://www.golynx.com/core/fileparse.php/97315/urlt/8-21-2025-Finance-Audit-Committee-Pkg.pdf
  38. C40 https://www.golynx.com/core/fileparse.php/97315/urlt/2-19-2026-Finance-Audit-Committee-Pkg.pdf
  39. C41 https://www.golynx.com/core/fileparse.php/97315/urlt/2-19-2026-Finance-Audit-Committee-Pkg.pdf
  40. C42 https://www.golynx.com/core/fileparse.php/97315/urlt/2-19-2026-Finance-Audit-Committee-Pkg.pdf
  41. C43 https://www.golynx.com/core/fileparse.php/97315/urlt/2-19-2026-Finance-Audit-Committee-Pkg.pdf
  42. C44 https://www.golynx.com/core/fileparse.php/97315/urlt/9-17-2026-Board-Report-Pkg2.pdf
  43. C45 https://www.golynx.com/core/fileparse.php/97315/urlt/9-17-2026-Board-Report-Pkg2.pdf
  44. C46 https://www.golynx.com/core/fileparse.php/97315/urlt/9-17-2026-Board-Report-Pkg2.pdf
  45. C47 https://www.golynx.com/core/fileparse.php/97315/urlt/9-17-2026-Board-Report-Pkg2.pdf
  46. C48 https://www.golynx.com/core/fileparse.php/97315/urlt/10-15-2026-Finance-Audit-Committee-Pkg.pdf
  47. C49 https://www.golynx.com/core/fileparse.php/97315/urlt/10-22-2026-Oversight-Committee-Pkg.pdf
  48. C50 https://www.golynx.com/core/fileparse.php/97315/urlt/10-22-2026-Board-Report-Pkg.pdf
  49. C51 https://www.orlando.gov/News/Press-Releases/2020-Press-Releases/Time-to-Charge-Up-Orlando-City-of-Orlando-OUC-and-LYNX-partner-to-Unveil-the-First-Zero-Emission-Electric-LYMMO-Bus-to-the-LYNX-Fleet