Did Kissimmee widen Thacker Avenue by June 2025, as promised?

The Roadmap Reckoner · Kissimmee, Florida (Thacker Avenue, between Flora Boulevard and Osceola Parkway) · last checked 2026-10-30

VerdictPENDING, OVERDUE (by about 16 months)
PromiserCity of Kissimmee
PlaceKissimmee, Florida (Thacker Avenue, between Flora Boulevard and Osceola Parkway)
Promised2025-06-30 (construction "7/1/2024" to "6/30/2025", the city's Jan. 2024 request to the Florida Senate)
Delivered / statusNot complete: still listed under Capital Projects (5-Yr Plan) in the city's Aug. 25, 2026 budget; no construction contract award found in 36 months of Commission records; the state's $250,000 was vetoed
Last checked2026-10-30

Verdict: PENDING, OVERDUE, by about 16 months. In January 2024 the City of Kissimmee asked the state to help pay for "the remaining two lanes of an important collector road within the city, Thacker Avenue" [C1, C5], with construction to start on "7/1/2024" [C2] and finish by "6/30/2025" [C3]. On August 25, 2026, the city's budget still listed "Thacker Ave Widening" under "Capital Projects (5-Yr Plan)" [C12, C12b, C12c]. In the City Commission's published agenda outlines and minutes for its 118 meetings over three years, the trace for this entry found no award of a construction contract for the widening. The state money the city asked for did not arrive: the Legislature appropriated $250,000 of the $500,000 requested [C6, C8c], and that line is on the Governor's veto list [C9].

Last checked: October 30, 2026.

Re-checked October 30, 2026. The City Commission has met once since the last check, on October 20, 2026 [C15], and the minutes of its October 6 meeting are now posted [C16]. Thacker Avenue is not an item in either meeting's record: it appears nowhere in the October 20 agenda and its 324-page packet, or in the October 6 minutes [the re-check's census]. The city's Projects list still shows "13 Result(s) Found", and the widening is on neither of its two pages [C17]. The Engineering Division page does not mention it [C18]. One web search for news of the widening found nothing newer. The verdict is unchanged; the delay is counted to this check.

The promise

The City of Kissimmee's request to the Florida Senate, Local Funding Initiative Request #3330 for fiscal year 2024-25, "Date of Request 01/10/2024" [C5]:

"In an effort to keep up with the unprecedented growth in the region, the City of Kissimmee seeks funding to construct the remaining two lanes of an important collector road within the city, Thacker Avenue. This is an important connection to one of the major arterial roads within the city, Osceola Parkway. In addition to increasing capacity by constructing two lanes, the project will add two signalized intersections, improve stormwater drainage, and add sidewalks to improve pedestrian connectivity in an area with two elementary schools, retail centers, and thousands of residential and multifamily units." [C1, C1b]

The same request gave the dates: "What is the estimated start date of construction? 7/1/2024" [C2] and "What is the estimated completion date of construction? 6/30/2025" [C3]. On the money, it said: "the city is in need of additional funding to complete this $7 million project. The city currently has $6.5 million budgeted in its CIP." [C4]

Timeline

What changed, and why, in the record's own words

What it cost

What is still open

What this entry did not check

Sources

  1. C1 https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  2. C1b https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  3. C2 https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  4. C3 https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  5. C4 https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  6. C5 https://www.flsenate.gov/PublishedContent/Session/FiscalYear/FY2024-25/LocalFundingInitiativeRequests/FY2024-25_S3330.pdf
  7. C6 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=7374,plainText=false)
  8. C7 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=7461,plainText=false)
  9. C8 https://www.flsenate.gov/Session/Bill/2024/5001/BillText/er/PDF
  10. C8b https://www.flsenate.gov/Session/Bill/2024/5001/BillText/er/PDF
  11. C8c https://www.flsenate.gov/Session/Bill/2024/5001/BillText/er/PDF
  12. C9 https://flcourts-media.flcourts.gov/content/download/2443705/file/FY_2024-25_Veto_List.pdf
  13. C10b https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=7834,plainText=false)
  14. C10c https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=7834,plainText=false)
  15. C11 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=8376,plainText=false)
  16. C11b https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=8376,plainText=false)
  17. C12 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=11097,plainText=false)
  18. C12b https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=11097,plainText=false)
  19. C12c https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=11097,plainText=false)
  20. C13 https://www.kissimmee.gov/Projects
  21. C13d https://www.kissimmee.gov/Projects
  22. C14 https://www.kissimmee.gov/My-Government/City-Departments-Offices/Public-Works-Engineering/Engineering
  23. C15 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=11181,plainText=false)
  24. C16 https://kissimmeefl.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=11194,plainText=false)
  25. C17 https://www.kissimmee.gov/Projects
  26. C18 https://www.kissimmee.gov/My-Government/City-Departments-Offices/Public-Works-Engineering/Engineering